Infrastructure of Cynda Aluminum Co., Ltd Start

View:3890 Edit:2014-01-06 12:40

       As the first pilefoundation was laid down steadily, infrastructure of Cynda, subsidiary corporationof Cyma, started on Jan 6th.2014.

      Cynda is located inMa’anshan Undertake Industrial Transfer Demonstration Park, is bordered by WuhuEconomic Development Zone, away from Cyma 30 minutes by car, covers an area of37000 square meters, the project planning a total construction area of 25000square meters.

     This constructionis for Phase I, with 5,000 square meters of plant building, 3000 square metersof R&D office building. The project is scheduled to be completedaccepted on July 26, the first 3000T extrusion line related supportingequipment will be put into production in early Oct. Phase Ⅱ of the project isexpected to start in Sep.2015.